Green Energy Corridors

Government Schemes & Missions · Sectoral missions

What it is

Dedicated transmission built to evacuate renewable power from resource-rich zones. Phase I covered about 9,700 ckm of lines and 22,600 MVA of substation capacity across eight states; Phase II targets roughly 10,750 ckm and 27,500 MVA at a cost near Rs 12,031 cr with 33% central assistance

The National Transmission Plan seeks 648,190 ckm by FY32

Impact on industries

  • Purpose-built evacuation removes the chicken-and-egg problem of generators waiting for lines and lines waiting for generators
  • Creates a defined, government-backed order pipeline for tower, conductor, substation and EPC suppliers
  • Required build rates are far above historical achievement, so the plan assumes an execution step-change that has not yet been demonstrated
  • Transmission planning has historically synchronised with thermal timelines of 36-60 months, which no longer matches renewable build speed